Prairie Valley Road and Rosedale Avenue Progress Report
SCHEDULE IS SUBJECT TO CHANGE
During the weeks of April 4th to April 15th
Rosedale Avenue
Rosedale Avenue is near completion with only some minor irrigation touch-ups on road and landscaping to take place over the next couple of weeks. This includes ground finish at the back of the sidewalks to bring the private property back to their original state. Clean up of streets and sidewalks will also take place by the middle of the month.
Prairie Valley Road
The contractor is currently completing installation of irrigation and placing top soil into the medians and boulevard planting areas on Prairie Valley Road and in the roundabouts. Landscaping in these areas should be done next week followed by construction of the remaining Allen Block walls. Once this is complete the contractor will be placing the required material at the back of the sidewalks to tie into private property.
We are still working towards scheduling the installation of the remainder of the thermoplast cross-walks when the weather is warmer and dryer. Completion of a few items outside the scope of the project will follow such as the rock wall at the Funeral Home, the wrought iron railing and boardwalk at the Anglican Church.
During all of this work one should expect only minor delays. Single lanes may be closed for brief periods of time but we do not anticipate further full road closures.
Devon van der Meulen, AScT
Deputy Director of Engineering and Public Works
250-404-4075
Kind Regards,
Raymond
Raymond MAASKE, BBA, CCC, ATM-B
Owner/Agent
5707 Impett Place,
Summerland, BC
V0H 1Z4 CanadaWebsite: http://www.HomeStarRealty.ca
E-mail: raymond@HomeStarRealty.ca
Phone: 250.488.8764
No comments:
Post a Comment